Published Sep 16, 2010
ROXBURY — Selectmen have learned that construction planned for this month on a 22-turbine wind farm atop local hills likely won't happen until next year.
In fact, no on-site work has been done this year on Record Hill Wind's $120 million project because of an appeal filed with the Maine Supreme Judicial Court in April. The wind project opponents' appeal has tied up financing pending a favorable decision, Record Hill principal Robert Gardiner said Wednesday.
Click here to read article and post comments on Sun Journal website.
In fact, no on-site work has been done this year on Record Hill Wind's $120 million project because of an appeal filed with the Maine Supreme Judicial Court in April. The wind project opponents' appeal has tied up financing pending a favorable decision, Record Hill principal Robert Gardiner said Wednesday.
Click here to read article and post comments on Sun Journal website.
This is good news.